← Projects

Cedar Ridge Apartments Ph. II

PRJ-2026-0141 · Multi-family · multifamily · Sacramento Metro
4820 Cedar Ridge Pkwy, Sacramento, CA

Status

Stage
Out for Bid
Days in stage
29
Confidence
high
Temperature
hot
Expected start
2 Nov 2026
Expected end
28 Feb 2027
Start window
2 Nov 2026 – 2 Nov 2026
Whisper→bid
42d
Forecast
$412,000

Parties

GC
Halvorsen Construction
Framers
Ironwood Framing — Roseville
Vasquez Framing

Roles are held per project, not as a column on the party — the same firm can be a GC on one building and a framer on another.

Plan versions

  1. A 10% plans 82,000 sq ft received 28 Jun · Bid set — layout only
  2. B 40% plans 84,500 sq ft +2,500 received 11 Aug · Wing added on the north elevation

Bid cycles

Round Reason Plans Opened Days open Invited
#1 Initial bid rev A (10%) 2 Jul – 8 Aug 37 0 of 0 quoted
#2 ← carried from #1 Plan revision rev B (40%) 14 Aug 29 (open) 1 of 2 quoted

Invitations

  • #2 Vasquez Framing Quoted received 14 Aug, 14-day window
  • #2 Ironwood Framing — Roseville Invited received 15 Aug, 13-day window · No response yet

Scope

Category Tier Quantity Intent Note
Roof truss Engineered to order 262,000 Board foot quoting
Floor truss Engineered to order 78,000 Board foot quoting
Wall panel Engineered to order by others Framer panelizing on site
Hardware Catalog 1 Each quoting Hanger package

3 of 4 lines are being quoted. Completeness against these lines warns rather than blocks (TKO-15) — a gap is a prompt, not a gate.